Waste-Heat Recovery Retrofit for a 300 kt/a Methanol Plant

The syngas leaving a coal-to-methanol plant reaches up to 280 ℃; the original design cooled it directly with water, wasting large amounts of low-grade heat every year. This project added a SAMIT fully-welded plate heat exchanger to recover syngas sensible heat for preheating boiler feed water, achieving cascaded energy utilization.

1. Project Background

Customer

A coal-chemical group in East China; 300 kt/a methanol capacity, with 2 × 220 t/h circulating fluidized-bed boilers.

Original Process

Syngas (280 ℃) was cooled to 40 ℃ in a shell-and-tube water cooler before entering the desulfurization tower, with the heat carried away and discharged by circulating water.

Core Pain Points

  • Annual heat waste equivalent to 3500 t of standard coal
  • High circulating-water pump energy
  • Bulky shell-and-tube equipment, tight footprint

2. Technical Solution

A SAMIT WB25 fully-welded plate heat exchanger was inserted upstream in the syngas line, using syngas sensible heat to preheat deaerated boiler feed water (104 ℃ → 155 ℃). The fully-welded structure withstands high-temperature corrosion from the trace H₂S in the syngas and requires no gasket maintenance.

ParameterSyngas Side (Hot)Boiler Feed-Water Side (Cold)
MediumSyngas (CO+H₂+trace H₂S)Deaerated feed water
Flow rate86000 Nm³/h180 t/h
Inlet temperature280 ℃104 ℃
Outlet temperature160 ℃155 ℃
Working pressure2.5 MPa5.4 MPa
Heat load13.5 MW

3. Process Flow

Methanol Syngas Waste-Heat Recovery Process Flow Syngas 280 ℃ 2.5 MPa · 86000 Nm³/h SAMIT WB25 Fully-Welded PHE 13.5 MW 85 m² · 254 SMO welded No gaskets 160 ℃ Desulfurization Tower Downstream process Sulfur removal Deaerated Feed Water 104 ℃ · 180 t/h 155 ℃ Boiler Economizer Steam saved Annual saving 85,000 GJ · 2900 t standard coal · CO₂ −7800 t · 11-month payback

4. Implementation

  • Phase 1 (Design & selection, 2 months): Site survey + operating-data collection + multi-option comparison (shell-and-tube / spiral / fully-welded); finally selected the SAMIT WB25 series, single-unit area 85 m².
  • Phase 2 (Manufacturing & supply, 3 months): 254 SMO plate laser welding + third-party supervision + factory hydrostatic test at 1.5× working pressure.
  • Phase 3 (Shutdown tie-in, 14 days): Used the annual overhaul window to remove the original water cooler and tie in the new PHE, with associated piping and control-system modifications.
  • Phase 4 (Start-up & commissioning, 3 days): Grid-connected operation; performance test reached 102% of design.

Key technical decision: 254 SMO was chosen over 316L because, although the H₂S content of the syngas is only 200 ppm, it still causes stainless-steel pitting at 280 ℃. 254 SMO contains 6% Mo, with a pitting resistance equivalent (PREN) ≥ 43, guaranteeing the 15-year design life.

5. Operating Results

Energy Savings

Annual heat recovery of 85,000 GJ, equivalent to 2900 t of standard coal; saves about 7.8 million RMB/year in steam cost.

Environmental Benefits

CO₂ reduction 7800 t/year, SO₂ reduction 45 t/year, helping the enterprise pass environmental inspections.

Footprint Optimization

The fully-welded PHE occupies only 4.8 m², an 83% reduction versus the original shell-and-tube (28 m²), freeing up plant space.

6. Lessons Learned

Coal-chemical waste-heat recovery must focus on medium corrosivity (H₂S, Cl⁻) and the temperature/pressure rating. The keys in this case: ① selecting fully-welded over shell-and-tube, quadrupling the heat-transfer coefficient; ② selecting 254 SMO to handle high-temperature H₂S corrosion; ③ using the annual overhaul window for the shutdown tie-in so production was unaffected. This model is replicable for ammonia synthesis, ethylene glycol, coal-to-liquids, and similar coal-chemical units.