2×600 MW Power Plant Closed-Cooling Water PHE

The closed-cooling-water system in a power plant is the core subsystem that supplies constant-temperature cooling water to key auxiliary equipment such as the main-engine lube-oil cooler, generator hydrogen cooler, and feed-water-pump lube-oil cooler. This project addressed the severe scaling and 35% capacity loss of the original shell-and-tube closed-cooling-water heat exchangers at a 2×600 MW supercritical coal-fired unit in Northwest China, replacing them entirely with SAMIT large plate heat exchangers.

1. Project Background

Customer

A state-owned power company in Northwest China; 2×600 MW supercritical coal-fired units, commissioned in 2012.

Original Equipment

2 shell-and-tube closed-cooling-water coolers (one per unit), cooling area 850 m².

Original Issues

  • Sediment deposition on the open-water (reservoir) side
  • 1.5 mm scaling on tube walls
  • Heat-transfer capacity down 35%
  • Required 2 shutdown cleanings per year

2. Technical Solution

SAMIT BR0.8 large plate heat exchangers replaced the original shell-and-tube units; each unit is equipped with 2 PHEs (one duty, one standby), with a heat-transfer area of 320 m² each. The open-water-side plates use a thickened corrugation design to handle sediment-laden water, with a 3.5 mm plate gap to prevent clogging.

ParameterClosed-Cooling-Water Side (Hot)Open-Cooling-Water Side (Cold)
MediumDemineralized deaerated water (closed)Reservoir once-through water (trace sediment)
Inlet/outlet temp.45 / 33 ℃25 / 36 ℃
Flow rate1200 m³/h1500 m³/h
Pressure ratingPN10PN10
Pressure drop45 kPa50 kPa
Heat load18 MW (per unit)
Plate material316L316L (thickened corrugation)

3. Process Flow

Power-Plant Closed-Cooling-Water SAMIT PHE Flow Main-Engine Lube Oil Generator H2 Cooling Feed-Pump Lube Oil 45 ℃ return SAMIT BR0.8 320 m² PHE 316L thickened corrugation 18 MW · 1 duty 1 standby 33 ℃ supply Reservoir Water 25 ℃ trace sediment 1500 m³/h 36 ℃ discharge → Cooling tower → Reservoir DCS Remote Monitoring + Outlet-Temp Feedback PHE outlet temp steady-state deviation ≤ ±1 ℃ CIP In-line Back-Flush (quarterly) Auto-starts back-flush when ΔP exceeds threshold 18 MW per unit · 4 units in parallel · 5 years without shutdown cleaning

4. Implementation

  • Original equipment removal: Used a 45-day unit overhaul window to remove the 2 shell-and-tube units (32 t each).
  • New equipment installation: 4 SAMIT BR0.8 PHEs (8 t each), single-person hoisting into place, no heavy machinery required.
  • Commissioning: 168-hour full-load trial run; closed-cooling-water outlet stable at 33 ± 0.5 ℃, K value 5200 W/(m²·K).

Key technology: To address the sediment in the reservoir water, the plates use a thickened corrugation (3.5 mm depth) + 316L stainless steel. A 20% wider corrugation maintains turbulence while lowering the per-channel pressure drop, so sediment is less likely to deposit. With the CIP back-flush connection, a 30-minute in-line cleaning each quarter restores initial performance.

5. Operating Results

Heat Transfer Capacity

K value raised from 3200 to 5200 W/(m²·K), up 62%.

Footprint & Weight

Equipment weight down 75%, plant-room footprint saved 60%.

O&M Cycle

Shutdown-cleaning cycle extended from half a year to 5 years (in-line back-flush suffices).

6. Lessons Learned

The core of a power-plant closed-cooling-water retrofit is "handling the water quality." The original shell-and-tube equipment is extremely sensitive to sediment-laden water; just 1.5 mm of scaling can cut heat-transfer capacity by 35%. The SAMIT thickened-corrugation PHE + in-line CIP back-flush solution fundamentally resolves this, with a footprint only 1/4 that of a shell-and-tube unit — especially suited to the tight retrofit conditions of a power-plant room.